SFMTA Street Changes Improve Safety in the Tenderloin

SFMTA Street Changes Improve Safety in the Tenderloin
By Samantha Serafica

 

Protected bike lane and active flex space along the 300 block of Golden Gate

Protected bike lane and active flex space along the 300 block of Golden Gate

Between 2015-2019, the average rate of a person getting hit by a vehicle while walking or biking along the Tenderloin stretch of Golden Gate Avenue and Leavenworth Street was every nine days. The Tenderloin is a densely populated and diverse community located in the heart of San Francisco. It is home to high concentrations of seniors, children, people of color, people experiencing homelessness and people with limited-English proficiency – many of whom live below the poverty line. These groups are most at risk of dying or being severely injured in traffic collisions.

Because of these concerns, the SFMTA launched two quick-build projects on Golden Gate Avenue and Leavenworth Street with preliminary design phases in February 2020. Considering their similar traffic calming goals, physical proximity and shared audience, we pursued a joint outreach campaign for both projects. SFMTA staff began this outreach through door-to-door canvassing, walkalongs, in-person meetings and emails to engage directly with stakeholders and collect project feedback before starting design.

Facing the Pandemic

Unfortunately, public health restrictions associated with the emerging COVID-19 healthy emergency led to a hold on both projects so that staff could allocate resources to address other critical issues that began to arise. To address immediate social distancing and physical space needs in the Tenderloin, the SFMTA worked with community organizations like St. Anthony’s, GLIDE and Tenderloin Community Benefit District (TLCBD) to implement several street improvements such as block closures, physical distancing lanes and temporary vehicle restrictions.

When the projects resumed in fall 2020, COVID-19 health and safety protocols were still in effect and pushed many meetings, typically held in-person, to online formats. We also partnered with the Tenderloin People’s Congress to hold virtual toolkit forums, community workshops and other conversations.

In place of a traditional, one-time, in-person event, staff created a virtual open house with interactive features and information about the projects. Published in seven different languages, the site remained open over a five-week period, allowing greater flexibility for people to view the information and provide feedback. Staff also hosted virtual office hours to provide space for questions and additional comments. Following the virtual open house, both projects held a public hearing in April 2021 and were cleared to start construction in May.

Impact

Every street in the Tenderloin is on the city’s Vision Zero High Injury Network, the 13% of city streets where 75% of severe and fatal collision occur. The COVID-19 pandemic only exacerbated the challenges of addressing the safety needs of the neighborhood. Now, our recently constructed quick-builds on Golden Gate Avenue and Leavenworth Street are helping to address the unsafe vehicle speeds and failures to yield that have made up the majority of traffic incidents in the Tenderloin.  

The relationships built from the Safer Taylor project provided a foundation to continue conversations with the community about traffic safety improvements in the neighborhood. Staff began outreach through door-to-door canvassing, walkalongs, in-person meetings and emails to engage directly with stakeholders and collect project feedback before starting design.

Throughout construction, SFMTA staff continued to collaborate with local partners such as Code Tenderloin and TLCBD to provide construction notifications to businesses and residents on the corridors. Both Golden Gate and Leavenworth street changes brought innovative quick-build improvements to the Tenderloin, such as an active flex space, and bringing these projects to life under COVID-19 required creativity, flexibility and strong community support.

What’s Next

Partnering with community organizations allows SFMTA staff to engage with stakeholders that would have otherwise been unreachable due to public safety concerns. While quick-build construction is complete, our work in the Tenderloin will continue. Some next steps include evaluating the quick-builds, exploring potential future projects and transitioning some of our COVID-19 emergency streets to quick-build improvements. Community partnerships with local groups and individual residents will continue to sustain and strengthen our work in the Tenderloin.

 

 



Published June 18, 2021 at 05:23AM
https://ift.tt/3xv6Lhr

Nhận xét

Bài đăng phổ biến từ blog này

Review sách Hackers IELTS Reading

Sách “Hackers IELTS” phù hợp cho bạn đang muốn tự ôn luyện tại nhà nhưng không biết nên chọn sách nào học cho hiệu quả và khoa học. Bộ sách “Hackers IELTS” được các chuyên gia tin tưởng giới thiệu cho những bạn chưa biết gì về IELTS, không biết cấu trúc đề thi IELTS gồm những phần nào,…thì “Hackers IELTS” rất phù hợp với những đối tượng này. Xem thêm bài viết đang được quan tâm nhất: Review sách... Bạn hoàn toàn có thể đạt 6.5 IELTS trở lên là điều không khó nếu như bạn biết cách sắp xếp lộ trình học sao cho logic và thêm việc lựa chọn 1 vài tài liệu thực sự hay và dễ học, thì mọi nút thắt đều được gỡ bỏ. Hàng nghìn độc giả đã mua và nêu cảm nhận rất tốt về bộ sách này chính là minh chứng cho việc “Hackers IELTS” sẽ giúp bạn làm được điều mà bạn mong ước. Review sách Hackers IELTS Reading Nội dung chính BOOK REVIEW “Hackers IELTS” Giới thiệu chung Ưu điểm Bố cục mỗi bài gồm Khuyết điểm Kết luận BOOK REVIEW  “Hackers IELTS” Tên sách: Hackers IELTS Reading Nhà xuất bản: Nhà xuất bản thế

Tổng hợp đề thi IELTS Writing 2023 kèm bài mẫu chi tiết – Cập nhật liên tục

Sau khi đã vững phần kiến thức chung, hẳn các bạn thí sinh sẽ rất muốn tiến hành vào việc giải đề để góp thêm kinh nghiệm vào việc luyện thi IELTS nói chung và thi viết nói riêng. Dưới đây sẽ là phần tổng hợp đề thi và bài mẫu IELTS Writing 2023 – Cập nhật liên tục, mời các bạn tham khảo qua nhé! Tổng hợp đề thi IELTS Writing 2023 kèm bài mẫu chi tiết – Cập nhật liên tục Đề IELTS Writing Tháng 01/2023 Ngày 04/01/2023 Task 1 Table – how many and why people from oversea and from the UK travel to London in 2 years. Task 2 Nowadays, not enough students choose science subjects in university in many countries. What are the reasons for this problem? What are the effects on society? Ngày 05/01/2023  Task 1 The percentage of people who were born in Australia and who were born outside Australia living in urban, rural and town between 1995 and 2010. Summarise the information by selecting and reporting the main features, and make comparisons where relevant.

TỔNG HỢP BÀI MẪU IELTS WRITING QUÝ 2/2022 

Đây là tổng hợp đề thi thật IELTS Writing Quý 2/2022 và kèm bài giải cùng phân tích chi tiết, các bạn đã đăng kí và chuẩn bị thi trong quý 3/2022 cùng tham khảo và luyện tập thật kĩ nhé. Ngày 07/05/2022 Task 1: The maps show the village of Pebbleton 20 years ago and now.  Summarise the information by selecting and reporting the main features, and make comparisons where relevant.  The two maps detail the town of Pebbleton 20 years in the past and the present day. Overall, Pebbleton has grown exponentially with the expansion of road infrastructure , as well as the building of additional dwellings and recreational amenities , changing the town into a more urbanised one. Initially, Pebbleton was an undeveloped peninsula connected to the mainland through Roadbridge, which was the only route to get to school on the opposite side of the river 20 years ago. A playing field ran horizontally along Old Ford Road in the central section, and a film studio filled the southern port