Chuyển đến nội dung chính

Reimagine Potrero Yard with Us – Summer Milestones

Reimagine Potrero Yard with Us – Summer Milestones
By Adrienne Heim

A rendering of the future modernized Potrero Yard

A potential rendering of the future modernized Potrero Yard

The Potrero Yard Modernization Project will rebuild the existing Potrero bus yard to ensure we maintain our bus fleet as efficiently as possible and enhance the facility’s resilience to climate change and other natural disasters. The Project will also ensure our staff is able to perform their work in a safe and efficient way and address the City’s broader goals for new housing and affordable housing.  The Project has issued a Request for Qualifications (RFQ), an important step for modernizing the yard.

The Project Concept

The modern yard will be able to store 213 buses, increasing capacity by approximately 50%.

In addition, the facility will include the following features:

  • LEED Gold Certification
  • An elevated structural and seismic building standard
  • Infrastructure for battery-electric buses
  • Centralized location for Street Operations - Muni’s “first responders”
  • Centralized, modern space for Muni operator training
  • Active ground floor uses on Bryant, and possibly 17th streets

“This exciting project will help fix two of the city's most pressing issues: lack of affordable housing and unreliable transit service,” said Alexander Hirji, Potrero Yard Neighborhood Working Group member and San Francisco Youth Commissioner. “The yard portion of the Project allows the SFMTA to maintain buses effectively, send them out to the riders, and it allows for future bus technology innovations in years to come. Up top, the affordable housing portion allows this city to make strides toward its goals for providing quality affordable housing to residents. This project will shape the Agency for many decades, and in a good, sustainable, and equitable way.”

An image showing a three level bus yard with mixed-use housing on top

A modernized Potrero Yard would have multiple uses.

Housing on Top of the Yard

An image of the Potrero Yard

Potrero Yard is home to much of Muni's trolleybus fleet

The SFMTA is proposing up to 575 rental units of housing with an initial affordability target of 50%. The city’s committed to addressing the shortage of affordable housing and is therefore challenging potential developers to seek additional funds to maximize the affordability percentage, up to as much as 100% affordable. Many factors informed the proposed project’s size and unit count, such as building height, massing, financial feasibility and shadows on Franklin Square.

Two months ago, virtual community conversations were hosted to provide a refresher about the project and discuss where we are in the process. If you were unable to attend, please listen to the June 6 conversation to hear the project team and members of the community discuss the project. 

We’re excited to announce that we’ve achieved three major milestones last week:

  1. The Project’s Request for Qualifications (RFQ) was issued to begin the developer procurement process followed by a press release

The RFQ is the first of a two-step process to bring a developer partner under contract with the city. This stage is to pre-qualify a group of professionals who have the experience and financial backing to successfully complete this project. Ideally, we will end up with three qualified developer teams. 

The second step is to ask those pre-qualified teams for project proposals as part of the Request for Proposal (RFP) stage, which will end up in the selection of a single developer partner.

  1. Special legislation was introduced by the Board of Supervisors last Tuesday, August 18, to set rules for a long-term agreement with a developer team that would design, build, finance, operate and maintain the new yard.

The legislation obligates the project to prevailing wages, a Local Business Enterprise (LBE) program, the city’s local hire policy and first source hiring ordinance. The ordinance also allows payment of a design stipend for up to two unsuccessful respondent development teams. This special legislation will first be heard by the Budget and Finance Committee consisting of Supervisors Walton, Fewer and Mandelman.

  1. A meeting to introduce all the topic areas that will be covered in the environmental impact document (referred collectively as the “project scope”) will be held by the San Francisco Planning Department on Wednesday, September 2, beginning at 6:00 p.m. 

You may also view a video presentation by SF Planning for the project and provide comments to cpc.PotreroYardEIR@sfgov.org concerning the scope of the Environmental Impact Report (EIR) until 5:00 p.m., September 18.

The meeting event will take place on Zoom: https://swca.zoom.us/s/92577630432/ Meeting ID: 925 7763 0432, or join by phone at 1.888.475.4499.

The purpose of the meeting is to collect comments from other regulatory agencies and the public on the draft scope. This is an opportunity for the public to add topic areas that SF Planning may not have included in their initial scoping process. More information can be found at the Planning Environmental Review Documents page under Potrero Yard Modernization Project – 2019-021884ENV.

Community Outreach

We will be tabling on Labor Day weekend, September 5 and 6, from noon to 5:00 p.m. at John O’Connell High School (Harrison Street between 18th and 20th streets) for the Carnaval San Francisco Latino COVID-19 Healing & Recovery – Salud es Poder event hosted by CANA-Carnaval San Francisco in partnership with the San Francisco Latino Task Force, community based organizations, health providers, and San Francisco City Departments.

We’re also planning to host English- and Spanish-language virtual community events to discuss the second step of the developer procurement process, the RFP, which we hope to issue in early 2021.

Learn more about the project by visiting www.sfmta.com/PotreroYard.

For more information, please email PotreroYard@sfmta.com or call us at 415.646.2223.

 



Published August 27, 2020 at 08:23AM
https://ift.tt/34OCz63

Nhận xét

Bài đăng phổ biến từ blog này

Đảm bảo tiêu chí Coherence và Cohesion trong IELTS Writing

Coherence & Cohesion là một trong bốn tiêu chí chủ chốt để đánh giá bài IELTS Speaking và Writing . Trong bài viết dưới đây, mời các bạn cùng IELTS Vietop tham khảo lại định nghĩa và những cách để đảm bảo tiêu chí Coherence và Cohesion trong IELTS Writing nhé! Tiêu chí Coherence và Cohesion trong IELTS Writing là gì? Tiêu chí Coherence & Cohesion là hai khía cạnh quan trọng trong việc đánh giá và phân tích một bài IELTS Writing. Trong đó: Tiêu chí Coherence và Cohesion trong IELTS Writing là gì Coherence (tính liên kết): Mức độ mà các ý tưởng trong văn bản liên kết với nhau một cách hợp lý và có tổ chức. Nó đảm bảo rằng các ý tưởng trong văn bản được trình bày theo một cách mạch lạc và dễ hiểu. Người viết cần sử dụng các từ nối, cụm từ, và cấu trúc câu hợp lý để giúp cho các ý tưởng trong văn bản được trình bày một cách logic và mạch lạc. Cohesion (tính gắn kết): Mức độ mà các câu trong văn bản gắn kết với nhau một cách hợp lý và tự nhiên. Nó đảm bảo rằng các câu t...

Talk about generation gap – Bài mẫu IELTS Speaking part 1, 2, 3

Talk about generation gap là dạng đề bài không quá dễ dàng đối với các bạn đang ôn luyện thi IELTS . Để có thể làm tốt chủ đề này, thí sinh cần nắm chắc từ vựng và cấu trúc về chủ đề Generation Gap (Chênh lệch thế hệ). Hôm nay, IELTS Vietop sẽ cung cấp cho bạn Talk about generation gap – Bài mẫu IELTS Speaking Part 1, 2, 3. 1. Từ vựng Talk about generation gap Generation gap /ˌʤɛnəˈreɪʃən ɡæp/ (n): Khác biệt thế hệ Ageism / ˈeɪˈʤɪɪzᵊm/ (n): Phân biệt đối xử dựa trên độ tuổi Technology divide / tɛkˈnɑləʤi dɪˈvaɪd/ (n): Sự khác biệt về sử dụng công nghệ Cultural shift /ˈkʌlʧərəl ʃɪft/ (n): Sự thay đổi văn hóa Traditional values /trəˈdɪʃənəl ˈvæljuz/ (n): Giá trị truyền thống Intergenerational conflict /ˌɪntərˈʤɛnəˈreɪʃənəl ˈkɑnflɪkt/ (n): Xung đột đa thế hệ Communication breakdown /kəmˌjunəˈkeɪʃən ˈbreɪkˌdaʊn/ (n): Mất liên lạc trong giao tiếp Respect for elders /rɪˈspɛkt fɔr ˈɛldərz/ (n): Sự tôn trọng người lớn tuổi Lifestyle differences /ˈlaɪfˌstaɪl ˈdɪfərənsɪz/ (n)...

Reading Practice: Toxic stress a slow wear and tear

A. Our bodies are built to respond when under attack. When we sense danger, our brain goes on alert, our heart rate goes up, and our organs flood with stress hormones like cortisol and adrenaline. We breathe faster, taking in more oxygen, muscles tense, our senses are sharpened and beads of sweat appear. This combination of reactions to stress is also known as the “fight-or-flight” response because it evolved as a survival mechanism, enabling people and other mammals to react quickly to life-threatening situations. The carefully orchestrated yet near-instantaneous sequence of hormonal changes and physiological responses helps someone to fight the threat off or flee to safety. Unfortunately, the body can also overreact to stressors that are not life-threatening, such as traffic jams, work pressure, and family difficulties. B. That’s all fine when we need to jump out of the way of a speeding bus, or when someone is following us down a dark alley. In those cases, our stress is considere...