Reimagine Potrero Yard with Us – Summer Milestones

Reimagine Potrero Yard with Us – Summer Milestones
By Adrienne Heim

A rendering of the future modernized Potrero Yard

A potential rendering of the future modernized Potrero Yard

The Potrero Yard Modernization Project will rebuild the existing Potrero bus yard to ensure we maintain our bus fleet as efficiently as possible and enhance the facility’s resilience to climate change and other natural disasters. The Project will also ensure our staff is able to perform their work in a safe and efficient way and address the City’s broader goals for new housing and affordable housing.  The Project has issued a Request for Qualifications (RFQ), an important step for modernizing the yard.

The Project Concept

The modern yard will be able to store 213 buses, increasing capacity by approximately 50%.

In addition, the facility will include the following features:

  • LEED Gold Certification
  • An elevated structural and seismic building standard
  • Infrastructure for battery-electric buses
  • Centralized location for Street Operations - Muni’s “first responders”
  • Centralized, modern space for Muni operator training
  • Active ground floor uses on Bryant, and possibly 17th streets

“This exciting project will help fix two of the city's most pressing issues: lack of affordable housing and unreliable transit service,” said Alexander Hirji, Potrero Yard Neighborhood Working Group member and San Francisco Youth Commissioner. “The yard portion of the Project allows the SFMTA to maintain buses effectively, send them out to the riders, and it allows for future bus technology innovations in years to come. Up top, the affordable housing portion allows this city to make strides toward its goals for providing quality affordable housing to residents. This project will shape the Agency for many decades, and in a good, sustainable, and equitable way.”

An image showing a three level bus yard with mixed-use housing on top

A modernized Potrero Yard would have multiple uses.

Housing on Top of the Yard

An image of the Potrero Yard

Potrero Yard is home to much of Muni's trolleybus fleet

The SFMTA is proposing up to 575 rental units of housing with an initial affordability target of 50%. The city’s committed to addressing the shortage of affordable housing and is therefore challenging potential developers to seek additional funds to maximize the affordability percentage, up to as much as 100% affordable. Many factors informed the proposed project’s size and unit count, such as building height, massing, financial feasibility and shadows on Franklin Square.

Two months ago, virtual community conversations were hosted to provide a refresher about the project and discuss where we are in the process. If you were unable to attend, please listen to the June 6 conversation to hear the project team and members of the community discuss the project. 

We’re excited to announce that we’ve achieved three major milestones last week:

  1. The Project’s Request for Qualifications (RFQ) was issued to begin the developer procurement process followed by a press release

The RFQ is the first of a two-step process to bring a developer partner under contract with the city. This stage is to pre-qualify a group of professionals who have the experience and financial backing to successfully complete this project. Ideally, we will end up with three qualified developer teams. 

The second step is to ask those pre-qualified teams for project proposals as part of the Request for Proposal (RFP) stage, which will end up in the selection of a single developer partner.

  1. Special legislation was introduced by the Board of Supervisors last Tuesday, August 18, to set rules for a long-term agreement with a developer team that would design, build, finance, operate and maintain the new yard.

The legislation obligates the project to prevailing wages, a Local Business Enterprise (LBE) program, the city’s local hire policy and first source hiring ordinance. The ordinance also allows payment of a design stipend for up to two unsuccessful respondent development teams. This special legislation will first be heard by the Budget and Finance Committee consisting of Supervisors Walton, Fewer and Mandelman.

  1. A meeting to introduce all the topic areas that will be covered in the environmental impact document (referred collectively as the “project scope”) will be held by the San Francisco Planning Department on Wednesday, September 2, beginning at 6:00 p.m. 

You may also view a video presentation by SF Planning for the project and provide comments to cpc.PotreroYardEIR@sfgov.org concerning the scope of the Environmental Impact Report (EIR) until 5:00 p.m., September 18.

The meeting event will take place on Zoom: https://swca.zoom.us/s/92577630432/ Meeting ID: 925 7763 0432, or join by phone at 1.888.475.4499.

The purpose of the meeting is to collect comments from other regulatory agencies and the public on the draft scope. This is an opportunity for the public to add topic areas that SF Planning may not have included in their initial scoping process. More information can be found at the Planning Environmental Review Documents page under Potrero Yard Modernization Project – 2019-021884ENV.

Community Outreach

We will be tabling on Labor Day weekend, September 5 and 6, from noon to 5:00 p.m. at John O’Connell High School (Harrison Street between 18th and 20th streets) for the Carnaval San Francisco Latino COVID-19 Healing & Recovery – Salud es Poder event hosted by CANA-Carnaval San Francisco in partnership with the San Francisco Latino Task Force, community based organizations, health providers, and San Francisco City Departments.

We’re also planning to host English- and Spanish-language virtual community events to discuss the second step of the developer procurement process, the RFP, which we hope to issue in early 2021.

Learn more about the project by visiting www.sfmta.com/PotreroYard.

For more information, please email PotreroYard@sfmta.com or call us at 415.646.2223.

 



Published August 27, 2020 at 08:23AM
https://ift.tt/34OCz63

Nhận xét

Bài đăng phổ biến từ blog này

Review sách Hackers IELTS Reading

Sách “Hackers IELTS” phù hợp cho bạn đang muốn tự ôn luyện tại nhà nhưng không biết nên chọn sách nào học cho hiệu quả và khoa học. Bộ sách “Hackers IELTS” được các chuyên gia tin tưởng giới thiệu cho những bạn chưa biết gì về IELTS, không biết cấu trúc đề thi IELTS gồm những phần nào,…thì “Hackers IELTS” rất phù hợp với những đối tượng này. Xem thêm bài viết đang được quan tâm nhất: Review sách... Bạn hoàn toàn có thể đạt 6.5 IELTS trở lên là điều không khó nếu như bạn biết cách sắp xếp lộ trình học sao cho logic và thêm việc lựa chọn 1 vài tài liệu thực sự hay và dễ học, thì mọi nút thắt đều được gỡ bỏ. Hàng nghìn độc giả đã mua và nêu cảm nhận rất tốt về bộ sách này chính là minh chứng cho việc “Hackers IELTS” sẽ giúp bạn làm được điều mà bạn mong ước. Review sách Hackers IELTS Reading Nội dung chính BOOK REVIEW “Hackers IELTS” Giới thiệu chung Ưu điểm Bố cục mỗi bài gồm Khuyết điểm Kết luận BOOK REVIEW  “Hackers IELTS” Tên sách: Hackers IELTS Reading Nhà xuất bản: Nhà xuất bản thế

Tổng hợp đề thi IELTS Writing 2023 kèm bài mẫu chi tiết – Cập nhật liên tục

Sau khi đã vững phần kiến thức chung, hẳn các bạn thí sinh sẽ rất muốn tiến hành vào việc giải đề để góp thêm kinh nghiệm vào việc luyện thi IELTS nói chung và thi viết nói riêng. Dưới đây sẽ là phần tổng hợp đề thi và bài mẫu IELTS Writing 2023 – Cập nhật liên tục, mời các bạn tham khảo qua nhé! Tổng hợp đề thi IELTS Writing 2023 kèm bài mẫu chi tiết – Cập nhật liên tục Đề IELTS Writing Tháng 01/2023 Ngày 04/01/2023 Task 1 Table – how many and why people from oversea and from the UK travel to London in 2 years. Task 2 Nowadays, not enough students choose science subjects in university in many countries. What are the reasons for this problem? What are the effects on society? Ngày 05/01/2023  Task 1 The percentage of people who were born in Australia and who were born outside Australia living in urban, rural and town between 1995 and 2010. Summarise the information by selecting and reporting the main features, and make comparisons where relevant.

TỔNG HỢP BÀI MẪU IELTS WRITING QUÝ 2/2022 

Đây là tổng hợp đề thi thật IELTS Writing Quý 2/2022 và kèm bài giải cùng phân tích chi tiết, các bạn đã đăng kí và chuẩn bị thi trong quý 3/2022 cùng tham khảo và luyện tập thật kĩ nhé. Ngày 07/05/2022 Task 1: The maps show the village of Pebbleton 20 years ago and now.  Summarise the information by selecting and reporting the main features, and make comparisons where relevant.  The two maps detail the town of Pebbleton 20 years in the past and the present day. Overall, Pebbleton has grown exponentially with the expansion of road infrastructure , as well as the building of additional dwellings and recreational amenities , changing the town into a more urbanised one. Initially, Pebbleton was an undeveloped peninsula connected to the mainland through Roadbridge, which was the only route to get to school on the opposite side of the river 20 years ago. A playing field ran horizontally along Old Ford Road in the central section, and a film studio filled the southern port